In order for our engineering consultant to issue the structural engineer’s certification, he looks at the following main items:


1. Are the anchors on the front and back of the MH encased in concrete or are they galvanized steel?


2. Are there also anchors on each end that have straps parallel to the MH chasses and are these anchors likewise encased in concrete or galvanized?


3. Does the MH have sufficient wind (longitude & latitude) stabilizer braces?


4. Are they the galvanized anchors spaced every 5’4”, and have stabilizer braces & approved beam clamps.


5. Is the skirting intact and there are no substantial weed-eater holes or other damage?


6. Is the skirting properly braced?


7. Is the pier spacing sufficient for the current FLA codes